The
Millennium Bridge and access link lift were as their name implies, constructed
to mark the Millennium.
The lift
was provided to link Peters Hill and Pauls Walk for persons who are unable or
prefer not to use the adjacent stairs.
The Bridge
was featured in the film “Harry Potter and the Half Blood Prince”.
The success
of the Tate Modern Gallery on the South side of the Bridge has meant that the
bridge and lift has become a tourist draw and now takes considerably more
traffic than was originally envisaged. Consequently the use of the lift has
substantially increased.
The City of
London decided that the lift was in need of upgrading to cope with this
increased use. The plan was to ensure the lift was completed for the River
Pageant celebration for the Queens Diamond Jubilee as well as the fast
approaching Olympics and Para Olympics.
The City of
London appointed Dunbar & Boardman as consultants for this project and the
first task was to complete a detailed feasibility study of how these works
would be undertaken and the source most suitable equipment for the project.
Following
the report, the City of London undertook the necessary approvals for the
funding of the works from the Corporation and planners, due to the highly
sensitive location and sight lines to St Pauls Cathedral. Dunbar & Boardman
produced a detailed specification for the works and sought the most suitable
contractors.
Hütter
Aufzuge of Hamburg, Germany were selected as the engineers/ manufacturers for
the replacement lift as they have an extensive and proven track record of
inclined lifts, for both internal and external locations including lifts in
public areas such as metro systems.
Whilst
Hütter were able and willing to supply the equipment, they would seek a local
contractor to undertake the installation with their support and back up. This was also useful to ensure that the
installer was UK based for on-going maintenance.
Axis
Elevators have a reputation for special ‘one off’ installations in London and
the South and have successfully completed a number of complex projects for
Dunbar & Boardman and were therefore considered to be the most suitable
contractor to install this lift. Axis were subsequently appointed by the City
of London as the main contractor to supply and fit the inclined lift.
The
principle of the design was to ensure that wherever possible, conventional lift
parts were used to ensure maintainability and reliability as well as obtaining
the necessary notified body approvals and certification. This included the lift arrangement having a
counterweight rather than a closed loop rope tensioned system previously
utilised. Hence the use of a Ziehl Abegg
gearless machine, Ziehl drive and recovery system, Schneider “Lisa” control
panel, optically connected Sematic doors and VVVF door drives etc.
The doors
were a particular concern as the lift arrangement has entrances on opposing
sides of the car, which means coupling the doors conventionally is complex and
was a major contribution to unreliability on the original lift. The Sematic wireless system was selected due
to the car and landing doors being independently driven but connected via an
optical coupling making the system more tolerant to minor variations in the car
position due to load in the car or weather conditions. The equipment is also available with the
appropriate level of protection for an external installation.
Due to the
planning restriction the doors had to be glazed and the operator mounted on the
underside of the car which was the first time this type of Wireless Sematic
door system had been installed in this configuration.
Once the
necessary approvals had been agreed, instructions were placed and the
manufacturing could commence whilst the final stages of planning the site works
were undertaken. Due to the programme
completion dates the site work needed to be undertaken between January and May
2012. Consequently the site had to be fully weather proofed as well as having a
hoarding fully encapsulating the lift enclosure for public safety.
Fortunately
the winter weather was not as bad as recent years although recent water
proofing was extensively tested!
One issue
arose during the design stages was the relevant Regulations and Standards
applicable to the ‘lift’, as its angle of inclination was 13.6°. This meant it
fell outside of the strict interpretation of EN81, and could be technically
classified a ‘cable way’, even though the original lift was certified under the
Lift Directive.
During
Consultation with the HSE Transportation and Safety Unit it was agreed with the
Department for Transport, that provided the lift was the same platform size and
speed as existing, and complied with EN81, it could be certified under the Lift
Directive but would also satisfy the Essential Safety Requirements of the Cable
ways Directive (where applicable).
This was
completed and included in the Technical Dossier for Handover.
The lift
was completely replaced during this period including the supporting truss,
guide, car, entrance, drive etc. The only retained items were the original
glass enclosure and concrete supports.
The lift
was delivered in three stages from Germany then stored locally before being
brought to site as needed, due to the limited space available.
The main
components were inspected in the Hütter factory prior to dispatch by the City
of London and Dunbar & Boardman. The
installation process was aided by the co-operation of the FM team at Millennium
Bridge House as well as The City of London School who both adjoin the site.
The
installation was completed on time and the lift was available for public use
during the Jubilee River Festival weekend.
People
Involved
Client: City
of London - Steve Daley, Alan Prosser
Consultants: Dunbar & Boardman – Chris Meering, Tim
Piggott, Peter Boardman
Manufacturers:
Hütter Aufzuge – Achim Hütter, Deiter
Fehse
Installer: Axis Elevators – Ian Rutherford, Keith Hodges, Andrew
Longcroft, Bob Hobbs, Steve
Site Team: Lee Johnson, Steve Tiegan
Notified
Body: Lift Cert – Malcolm Miles
HSE
Transportation and Safety Unit: Robert Cooper and Adebayo Ige
Dept for Transport: Steve Berry
It’s hard to find knowledgeable people on this topic, but you sound like you know what you’re talking about! Thanks for sharing this with others external lift,
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteGet the services of the top Lift & Staircase Installer In London. Vetted Trades Online is having the best tradesmen providing Emergency lift Repair and Maintenance.
ReplyDelete